Portal Home > HVAC & Cleanroom > Cooling Load Sizing
Tool 6: HVAC Engineering

Preliminary HVAC Cooling Load & Tonnage Screening Estimator

Calculates sensible and latent heat gains (building envelope transmission, solar fenestration, occupants, equipment, and ventilation air), decoupled base/design BTU/h, commercial tonnage (TR), and circulating airflow (CFM).

✔ 1. Formula Verified → ⚡ 2. Engineering Screening → 📐 3. Default Heuristic Assumptions → ⚖ 4. Engineer Review Required
❄️ Space Heat Gain Parameters
sq.ft
Screening envelope transmission heuristic: 32.0 BTU/h per sq.ft.
People
Occupant thermal emission: 450 BTU/h per person (250 sensible + 200 latent) + 15 CFM/person fresh air.
Watts
Computers, servers, machinery, lighting (1 Watt = 3.412 BTU/h heat emission).
sq.ft
Solar fenestration screening heuristic: 75.0 BTU/h per sq.ft of exposed glazing.
Multiplier
Standard 10% design safety margin (1.10) applied to base sensible and latent heat gains.
📊 Tonnage & CFM Sheet
Preliminary Screening
Recommended Commercial Capacity
27.0 TR
Exact Required Tonnage: 26.64 TR (93.66 kW Cooling)
Base Heat Load (Pre-Safety)
2,90,590 BTU/h
Design Heat Load (+10% SF)
3,19,649 BTU/h
Total Circulating Airflow
10,655 CFM
Equivalent Electrical Cooling
93.66 kW
💬 Consult HVAC Solutions Team on WhatsApp

Engineering Screening Methodology & Assumptions

Default Screening Assumptions

This tool provides rapid preliminary screening and equipment capacity estimation. The following parameters represent default screening assumptions, not rigid ASHRAE standard mandates:

  • Envelope transmission: 32.0 BTU/h·ft² carpet area.
  • Solar fenestration: 75.0 BTU/h·ft² glass exposure.
  • Occupants: 450 BTU/h per person (250 sensible + 200 latent).
  • Fresh air ventilation: 15 CFM/person (ΔT = 25°F, ΔW = 0.007 lb/lb).
  • Airflow sizing factor: 400 CFM per Ton of Refrigeration (TR).

Contrast with Full ASHRAE Design

A formal ASHRAE cooling load calculation requires the Radiant Time Series (RTS) or Heat Balance (HB) method per ASHRAE Handbook - Fundamentals (Chapters 17 & 18) with hourly solar angle radiation, dimensionless Solar Heat Gain Coefficients (SHGC), composite multi-layer wall/roof U-factors, thermal storage factors, and ASHRAE Standard 62.1 ventilation schedules.

q_base = q_fabric + q_glass + q_people + q_equip + q_vent
q_design = q_base × Safety_Margin
Tonnage (TR) = q_design / 12,000 BTU/h
Airflow (CFM) = Tonnage × 400 CFM/TR
⚖ Statutory Notice & Engineering Disclaimer (Tier D Integration)

This calculation provides preliminary engineering screening and feasibility sizing. Project-specific chiller, VRF, or package unit procurement requires detailed room-by-room solar heat balance modeling, building orientation analysis, envelope U-factor verification, and psychrometric coil selection verified by a certified MEP consultant.